Agile Computing Authors: John Mertic, Carmen Gonzalez, Roger Strukhoff, Pat Romanski, Elizabeth White

News Feed Item

Suncor Energy reports 2012 fourth quarter results

All financial information, unless otherwise noted, is unaudited, in Canadian dollars, and has been prepared in accordance with Canadian generally accepted accounting principles (GAAP). Certain financial measures in this news release - namely operating ear

CALGARY, ALBERTA -- (Marketwire) -- 02/06/13 --

--  Operating earnings of $1.000 billion ($0.65 per common share) and a net
    loss of $562 million ($0.37 per common share). Net loss includes an
    after-tax impairment charge of $1.487 billion for the Voyageur upgrader
--  Cash flow from operations of $2.235 billion ($1.46 per common share). 
--  Average Oil Sands segment production of 378,700 barrels per day
    (bbls/d). Total average production of 556,500 barrels of oil equivalent
    per day (boe/d). 
--  Refining and Marketing caps record year for earnings and cash flow from
    operations, benefiting from lower feedstock cost from Suncor's Oil Sands
--  Sanction of the Hebron project offshore Newfoundland and Labrador. 
--  Firebag complex achieves 72% production growth from the fourth quarter
    of 2011. Stage 4 final project costs anticipated to be approximately 15%
    below budget.

Suncor Energy Inc. recorded fourth quarter 2012 operating earnings of $1.000 billion ($0.65 per common share), compared to $1.427 billion ($0.91 per common share) for the fourth quarter of 2011. The decrease in operating earnings compared to the fourth quarter of 2011 was due primarily to lower average price realizations in Oil Sands, a product mix for Oil Sands that included a lower proportion of sweet synthetic crude oil (SCO), and lower production from offshore assets completing planned maintenance. Suncor continued to absorb much of the impact of lower price realizations in the Oil Sands through its integration with its inland refineries that benefited from lower feedstock costs.

Cash flow from operations was $2.235 billion ($1.46 per common share) for the fourth quarter of 2012, compared to $2.650 billion ($1.69 per common share) for the fourth quarter of 2011. Cash flow from operations decreased due primarily to the same factors affecting operating earnings.

The net loss was $562 million ($0.37 per common share) for the fourth quarter of 2012, compared with net earnings of $1.427 billion ($0.91 per common share) for the fourth quarter of 2011. The net loss included an after-tax impairment charge of $1.487 billion for the Voyageur upgrader project. Return on capital employed (ROCE) (excluding major projects in progress) for the twelve months ended December 31, 2012 was 7.3%, compared to 13.8% for the twelve months ended December 31, 2011. The impairment of the Voyageur upgrader project impacted ROCE by approximately 4%.

"Our integrated model combined with our focus on operational excellence continues to add value to Suncor," said Steve Williams, Suncor president and chief executive officer. "First, our ability to capture margins through the integration of our oil sands feedstock to our inland refineries contributed significantly to generating close to $10 billion in cash flow from operations in 2012. Second, we have increased nameplate capacity of our Edmonton refinery by 5,000 barrels per day due to our focus on operational excellence. And finally, we've seen record oil sands production for the year while at the same time, our dedication to managing costs is anticipated to result in a capital savings on Firebag Stage 4 of approximately 15%."

Suncor's total upstream production during the fourth quarter of 2012 averaged 556,500 boe/d, compared to 576,500 boe/d during the fourth quarter of 2011.

Oil Sands production (excluding Suncor's proportionate share of production from Syncrude) contributed an average of 342,800 bbls/d in the fourth quarter of 2012, compared with fourth quarter 2011 production of 326,500 bbls/d. The increase in Oil Sands production was primarily due to the ramp up of production from the Firebag complex, partially offset by the impacts of planned and unplanned maintenance at upgrading facilities. At Firebag, average bitumen production increased to 123,400 bbls/d in the fourth quarter of 2012 from 113,000 bbls/d in the third quarter of 2012 and 71,700 bbls/d in the fourth quarter of 2011.

Cash operating costs for Oil Sands operations averaged $38.00/bbl in the fourth quarter of 2012, compared to $39.00/bbl in the fourth quarter of 2011. Cash operating costs per barrel were lower due to higher production volumes from the ramp up of Firebag volumes and consistent total cash operating costs, as compared to the fourth quarter of 2011.

Suncor's proportionate share of production from Syncrude contributed an average of 35,900 bbls/d of production during the fourth quarter of 2012, compared to 30,300 bbls/d in the fourth quarter of 2011.

The Exploration and Production segment contributed production of 177,800 boe/d in the fourth quarter of 2012, compared with production of 219,700 boe/d in the fourth quarter of 2011. The decrease was primarily due to planned maintenance events at Buzzard and Terra Nova, which were completed in the fourth quarter of 2012, and subsequent delays ramping up production, the ongoing suspension of the company's operations in Syria as a result of political unrest and international sanctions, and production declines in North America Onshore, partially offset by the restart of operations in Libya.

"Although we are pleased with our underlying cost discipline and performance trends," added Williams, "we know there are areas we need to improve. Our reliability at our oil sands upgraders and the delays associated with our Terra Nova planned maintenance were disappointing. However, we remain committed to a relentless focus on operational excellence to improve performance."

In the company's downstream Refining and Marketing segment, total refined product sales averaged 87,000 cubic metres per day during the fourth quarter of 2012, compared to 81,600 cubic metres per day in the fourth quarter of 2011. This increase was due primarily to lower production in the fourth quarter of 2011 resulting from third-party hydrogen supply issues at the Edmonton refinery. Results for the segment continued to be strong, reflecting lower feedstock costs for Suncor's inland refineries and strong refinery utilization. Effective January 1, 2013, Suncor increased the nameplate capacity of the Edmonton refinery to 140,000 bbls/d from 135,000 bbls/d, due to demonstrated reliability and continuous improvement in operating efficiency.

Strategy and Operational Update

The company announced a $7.3 billion capital and exploration budget for 2013. Approximately $3.3 billion of this capital is expected to be directed towards growth projects, with a continued focus on capital discipline and the execution of high return projects. Approximately half of Suncor's growth capital is earmarked for advancing projects in the Exploration and Production segment, including Hebron, Golden Eagle, and development drilling and facilities at other East Coast Canada assets. Growth capital plans in the Oil Sands are balanced between advancing development plans for Oil Sands Ventures, building new infrastructure to enhance marketing flexibility and takeaway capacity, and commencing work on a variety of debottlenecking projects. Growth capital in the Refining and Marketing segment is expected to be focused on projects to prepare the Montreal refinery to receive shipments of western crude feedstock.

As previously announced, Suncor has been working with its respective partners to undertake detailed reviews of each of its planned Oil Sands Ventures growth projects, focusing on cost and quality with a view to generating long-term value for shareholders.

With respect to the Fort Hills mining project, the partners expect a sanction decision to occur in the second half of 2013. Suncor plans to provide an update on the targeted timing for a sanction decision on the Joslyn project when available.

Suncor's view is that the economic outlook for the Voyageur upgrader project is challenged. Suncor and its partner continue to work diligently towards determining an outcome for the project. The partners have been considering options for the project, including the implications of cancellation or indefinite deferral. No formal decisions regarding the project have been made and the partners continue to work toward a decision by the end of the first quarter of 2013. The Voyageur upgrader project cannot be sanctioned to proceed without the approval of both partners and in the case of Suncor, Suncor's board of directors. In the interim, Suncor and its partner have agreed to minimize expenditures on the project pending a decision.

Given the challenging economic outlook for the Voyageur upgrader project, at the end of the fourth quarter of 2012, the company performed an impairment test. Based on an assessment of expected future net cash flows, the company recorded an after-tax impairment charge of $1.487 billion, after which the company's carrying value for net assets relating to the Voyageur upgrader project as at December 31, 2012 was approximately $345 million.

At In Situ, the company commissioned the Firebag Stage 4 cogeneration units in the fourth quarter ahead of schedule, and is currently injecting steam into both well pads for Stage 4. Stage 4 continued to progress as the company achieved first oil from Stage 4 wells late in the fourth quarter of 2012. Stage 4 central processing facilities operated at 10% capacity throughout the quarter. The project is nearly complete and expected to come in approximately 15% under the most recent budget estimate of $2.0 billion. The company anticipates that bitumen production from the Firebag complex will continue to grow during 2013 and reach production capacity of approximately 180,000 bbls/d over the next year.

New assets were brought into service to support Oil Sands operations during the quarter: the Wood Buffalo pipeline, which connects the company's Athabasca terminal at the base plant in Fort McMurray to other third-party pipeline infrastructure in Cheecham, Alberta, and the first two of four new storage tanks in Hardisty, Alberta, which will connect to the Enbridge mainline pipeline in 2013.

"During the quarter we made good progress by constructing new infrastructure to enhance the takeaway capacity and marketing flexibility of our oil sands operations," said Williams. "These developments, coupled with our integrated model, put Suncor in an advantaged position as the industry works to address the challenges of moving oil sands crudes out of Alberta."

In the company's East Coast Canada operations, the company and the joint owners of Hebron announced project sanction in the fourth quarter of 2012; Suncor has a 22.729% interest in Hebron. The development plan includes a concrete gravity-based structure supporting an integrated topside deck to be used for production, drilling and accommodations. The estimated gross oil production capacity for Hebron is 150,000 bbls/d. Suncor's share of the project cost estimate provided by the project operator is approximately $3.2 billion. First oil is expected in late 2017. At Terra Nova, production from the largest of three drill centres resumed following the completion of the dockside maintenance program earlier in the year. The second drill centre was connected in January and is currently being commissioned. The third drill centre is expected to be reconnected in the third quarter of 2013, when damaged flow lines can be replaced. Despite the impact on production, the company currently expects to meet guidance.

In the company's International operations, although planned maintenance at Buzzard was completed in late October, the restart of production was delayed by power supply interruptions; however, production exiting 2012 was over 60,000 boe/d, which exceeded production rates prior to planned maintenance. In Libya, Suncor is currently working to restart exploration drilling in the first quarter of 2013. Production from Libya averaged 44,400 bbls/d during the fourth quarter of 2012, the highest level since the merger with Petro-Canada in 2009. Although Suncor's operations in Syria remain suspended, the company received $300 million of risk mitigation proceeds related to its Syrian assets during the quarter. The proceeds are subject to a provisional repayment should operations in Syria resume and, therefore, are recognized as a liability. As a result, Suncor reversed $177 million of the impairment charges it recorded against its assets in Syria earlier in the year.

In the company's North America Onshore operations, new wells in the Cardium oil formation in Western Canada were tied in and began producing in December 2012.

Suncor continued to return cash to shareholders through dividends and share repurchases. The company repurchased $408 million of its common shares in the fourth quarter of 2012, and returned more than $2.0 billion to shareholders through share repurchases and dividends in 2012.

Other Items

In January 2013, the company received a proposal letter from the Canada Revenue Agency (CRA) relating to the income tax treatment of the realized losses in 2007 on the settlement of the Buzzard derivative contracts. The company strongly disagrees with the CRA's position and will respond to the proposal letter; however, the CRA may proceed to issue a notice of reassessment (NOR) to increase the amount payable by approximately $1.2 billion. The company firmly believes it will be able to successfully defend its original filing position so that ultimately no increased income tax payable will result from the CRA's actions. However, notwithstanding the filing of an objection to dispute this matter, the company would be required to make a minimum payment of 50% of the amount payable under the NOR, estimated to be $600 million, which would remain on account until the dispute is resolved.

Suncor, effective as of December 27, 2012, amended and restated its Dividend Reinvestment and Optional Common Share Purchase Plan (the "Plan"). The Plan permits registered holders of common shares ("Common Shares") of Suncor who reside in Canada or the U.S. to have the dividends they receive on their Common Shares reinvested in additional Common Shares, in lieu of receiving their dividends in cash. In addition, participants enrolled in the Plan have the opportunity to make optional cash payments under the Plan towards the purchase of additional Common Shares. Full details of the amended and restatement Plan can be found on Computershare Trust Company of Canada's website at www.computershare.com.

Corporate Guidance

Suncor has revised the corporate guidance it previously issued on December 3, 2012. Effective January 1, 2013, Suncor increased the nameplate capacity of the Edmonton refinery to 140,000 bbls/d from 135,000 bbls/d, due to demonstrated reliability and continuous improvements in operating efficiency. As a result, Suncor revised the company's guidance to reflect a decrease in refinery utilization. Guidance for refinery throughput was not revised.

For further details regarding Suncor's 2013 revised corporate guidance, including certain outlook assumptions and other information, see www.suncor.com/guidance.

Non-GAAP Financial Measures

All financial information, unless otherwise noted, has been prepared in accordance with Canadian GAAP, specifically International Accounting Standard (IAS) 34 Interim Financial Reporting as issued by the International Accounting Standards Board, within Part 1 of the Canadian Institute of Chartered Accountants Handbook, which is within the framework of International Financial Reporting Standards (IFRS).

Certain financial measures in this news release - namely operating earnings, cash flow from operations, ROCE and Oil Sands cash operating costs - are not prescribed by Canadian GAAP. Operating earnings and Oil Sands cash operating costs are defined in the Non-GAAP Financial Measures Advisory section of Suncor's Q4 2012 Report to Shareholders dated February 5, 2013 (the "Report to Shareholders") and reconciled to GAAP measures respectively in the Consolidated Financial Information and the Segment Results and Analysis - Oil Sands section of the Report to Shareholders. Cash flow from operations and ROCE are defined and reconciled to GAAP measures in the Non-GAAP Financial Measures Advisory section of the Report to Shareholders.

These non-GAAP financial measures do not have any standardized meaning and therefore are unlikely to be comparable to similar measures presented by other companies. These non-GAAP financial measures are included because management uses the information to analyze operating performance, leverage and liquidity, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP.

Legal Advisory - Forward-Looking Information

This news release contains certain forward-looking statements and other information based on Suncor's current expectations, estimates, projections and assumptions that were made by the company in light of its experience and its perception of historical trends, including: expectations and assumptions concerning the accuracy of reserves and resources estimates; commodity prices and interest and foreign exchange rates; capital efficiencies and cost savings; applicable royalty rates and tax laws; future production rates; the sufficiency of budgeted capital expenditures in carrying out planned activities; the availability and cost of labour and services; and the receipt, in a timely manner, of regulatory and third-party approvals. All statements and other information that address expectations or projections about the future, and other statements and information about Suncor's strategy for growth, expected and future expenditures, commodity prices, costs, schedules, production volumes, operating and financial results and expected impact of future commitments are forward-looking statements. Some of the forward-looking statements and information may be identified by words like "expected", "guidance", "plans", "outlook", "continue", "focus", "could", "potentially" and similar expressions.

Forward-looking statements in this news release include references to the following expectations and plans: Suncor's $7.3 billion capital and exploration budget for 2013; with respect to the Fort Hills mining project, a decision around sanction will be made by the partners in the second half of 2013; Suncor and its partner will work towards a decision on the Voyageur upgrader project by the end of the first quarter of 2013; the economic outlook for the Voyageur upgrader project is challenged; the Firebag project will come in 15% under budget and bitumen production from the Firebag complex will reach production capacity of 180,000 bbls/d over the next year; the first two of four new storage tanks in Hardisty, Alberta will connect to the Enbridge mainline pipeline in 2013; Suncor's share of capital for the Hebron project will be approximately $3.2 billion, the estimated gross oil production capacity for Hebron will be 150,000 bbls/d and that first oil is expected in late 2017; the third drill centre for Terra Nova is expected to be reconnected in the third quarter of 2013, when damaged flowlines can be replaced; the company's assessment of asset impairment in Syria and for its Voyageur upgrader; and Suncor will be able to successfully defend its original filing position relating to the Buzzard derivative contracts and that no increased income tax payable ultimately should result from CRA's actions.

Forward-looking statements and information are not guarantees of future performance and involve a number of risks and uncertainties, some that are similar to other oil and gas companies and some that are unique to Suncor. Suncor's actual results may differ materially from those expressed or implied by its forward-looking statements, so readers are cautioned not to place undue reliance on them.

Additional risks, uncertainties and other factors that could influence financial and operating performance of all of Suncor's operating segments and activities include, but are not limited to, changes in general economic, market and business conditions, such as commodity prices, interest rates and currency exchange rates; fluctuations in supply and demand for Suncor's products; the successful and timely implementation of capital projects, including growth projects and regulatory projects; competitive actions of other companies, including increased competition from other oil and gas companies or from companies that provide alternative sources of energy; labour and material shortages; actions by government authorities, including the imposition of taxes or changes to fees and royalties, and changes in environmental and other regulations; the ability and willingness of parties with whom we have material relationships to perform their obligations to us; the occurrence of unexpected events such as fires, equipment failures and other similar events affecting Suncor or other parties whose operations or assets directly or indirectly affect Suncor; the potential for security breaches of Suncor's information systems by computer hackers or cyber terrorists, and the unavailability or failure of such systems to perform as anticipated as a result of such breaches; our ability to find new oil and gas reserves that can be developed economically; the accuracy of Suncor's reserves, resources and future production estimates; market instability affecting Suncor's ability to borrow in the capital debt markets at acceptable rates; maintaining an optimal debt to cash flow ratio; the success of the company's risk management activities using derivatives and other financial instruments; the cost of compliance with current and future environmental laws; risks and uncertainties associated with closing a transaction for the purchase or sale of an oil and gas property, including estimates of the final consideration to be paid or received, the ability of counterparties to comply with their obligations in a timely manner and the receipt of any required regulatory or other third-party approvals outside of Suncor's control that are customary to transactions of this nature; and the accuracy of cost estimates, some of which are provided at the conceptual or other preliminary stage of projects and prior to commencement or conception of the detailed engineering that is needed to reduce the margin of error and increase the level of accuracy. The foregoing important factors are not exhaustive.

The Report to Shareholders and Suncor's Annual Information Form/Form 40-F dated March 1, 2012, Annual Report to Shareholders and other documents it files from time to time with securities regulatory authorities describe the risks, uncertainties, material assumptions and other factors that could influence actual results and such factors are incorporated herein by reference. Copies of these documents are available without charge from Suncor at 150 6th Avenue S.W., Calgary, Alberta T2P 3E3, by calling 1-800-558-9071, or by email request to [email protected] or by referring to the company's profile on SEDAR at www.sedar.com or EDGAR at www.sec.gov. Except as required by applicable securities laws, Suncor disclaims any intention or obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events or otherwise.

Certain natural gas volumes have been converted to barrels of oil equivalent (boe) on the basis of one barrel to six thousand cubic feet. Any figure presented in boe may be misleading, particularly if used in isolation. A conversion ratio of one bbl of crude oil or natural gas liquids to six thousand cubic feet of natural gas is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead. Given that the value ratio based on the current price of crude oil as compared to natural gas is significantly different from the energy equivalency of 6:1, utilizing a conversion on a 6:1 basis may be misleading as an indication of value.

Suncor Energy is Canada's premier integrated energy company. Suncor's operations include oil sands development and upgrading, conventional and offshore oil and gas production, petroleum refining, and product marketing under the Petro-Canada brand. While working to responsibly develop petroleum resources, Suncor is also developing a growing renewable energy portfolio. Suncor's common shares (symbol: SU) are listed on the Toronto and New York stock exchanges.

For more information about Suncor Energy please visit our web site at www.suncor.com or follow us on Twitter @SuncorEnergy.

A full copy of the Report to Shareholders and the financial statements and notes (unaudited) can be downloaded at www.suncor.com/financialreporting or www.sedar.com or by calling 1-800-558-9071 toll-free in North America.

To listen to the conference call discussing Suncor's fourth quarter results, visit www.suncor.com/webcasts.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
@ThingsExpo has been named the Top 5 Most Influential M2M Brand by Onalytica in the ‘Machine to Machine: Top 100 Influencers and Brands.' Onalytica analyzed the online debate on M2M by looking at over 85,000 tweets to provide the most influential individuals and brands that drive the discussion. According to Onalytica the "analysis showed a very engaged community with a lot of interactive tweets. The M2M discussion seems to be more fragmented and driven by some of the major brands present in the...
In his general session at 19th Cloud Expo, Manish Dixit, VP of Product and Engineering at Dice, will discuss how Dice leverages data insights and tools to help both tech professionals and recruiters better understand how skills relate to each other and which skills are in high demand using interactive visualizations and salary indicator tools to maximize earning potential. Manish Dixit is VP of Product and Engineering at Dice. As the leader of the Product, Engineering and Data Sciences team a...
Personalization has long been the holy grail of marketing. Simply stated, communicate the most relevant offer to the right person and you will increase sales. To achieve this, you must understand the individual. Consequently, digital marketers developed many ways to gather and leverage customer information to deliver targeted experiences. In his session at @ThingsExpo, Lou Casal, Founder and Principal Consultant at Practicala, discussed how the Internet of Things (IoT) has accelerated our abil...
19th Cloud Expo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy. Meanwhile, 94% of enterpri...
SYS-CON Events announced today that Streamlyzer will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Streamlyzer is a powerful analytics for video streaming service that enables video streaming providers to monitor and analyze QoE (Quality-of-Experience) from end-user devices in real time.
You have great SaaS business app ideas. You want to turn your idea quickly into a functional and engaging proof of concept. You need to be able to modify it to meet customers' needs, and you need to deliver a complete and secure SaaS application. How could you achieve all the above and yet avoid unforeseen IT requirements that add unnecessary cost and complexity? You also want your app to be responsive in any device at any time. In his session at 19th Cloud Expo, Mark Allen, General Manager of...
Established in 1998, Calsoft is a leading software product engineering Services Company specializing in Storage, Networking, Virtualization and Cloud business verticals. Calsoft provides End-to-End Product Development, Quality Assurance Sustenance, Solution Engineering and Professional Services expertise to assist customers in achieving their product development and business goals. The company's deep domain knowledge of Storage, Virtualization, Networking and Cloud verticals helps in delivering ...
Intelligent machines are here. Robots, self-driving cars, drones, bots and many IoT devices are becoming smarter with Machine Learning. In her session at @ThingsExpo, Sudha Jamthe, CEO of IoTDisruptions.com, will discuss the next wave of business disruption at the junction of IoT and AI, impacting many industries and set to change our lives, work and world as we know it.
SYS-CON Events announced today that 910Telecom will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Housed in the classic Denver Gas & Electric Building, 910 15th St., 910Telecom is a carrier-neutral telecom hotel located in the heart of Denver. Adjacent to CenturyLink, AT&T, and Denver Main, 910Telecom offers connectivity to all major carriers, Internet service providers, Internet backbones and ...
The IoT industry is now at a crossroads, between the fast-paced innovation of technologies and the pending mass adoption by global enterprises. The complexity of combining rapidly evolving technologies and the need to establish practices for market acceleration pose a strong challenge to global enterprises as well as IoT vendors. In his session at @ThingsExpo, Clark Smith, senior product manager for Numerex, will discuss how Numerex, as an experienced, established IoT provider, has embraced a ...
Cloud based infrastructure deployment is becoming more and more appealing to customers, from Fortune 500 companies to SMEs due to its pay-as-you-go model. Enterprise storage vendors are able to reach out to these customers by integrating in cloud based deployments; this needs adaptability and interoperability of the products confirming to cloud standards such as OpenStack, CloudStack, or Azure. As compared to off the shelf commodity storage, enterprise storages by its reliability, high-availabil...
DevOps is being widely accepted (if not fully adopted) as essential in enterprise IT. But as Enterprise DevOps gains maturity, expands scope, and increases velocity, the need for data-driven decisions across teams becomes more acute. DevOps teams in any modern business must wrangle the ‘digital exhaust’ from the delivery toolchain, "pervasive" and "cognitive" computing, APIs and services, mobile devices and applications, the Internet of Things, and now even blockchain. In this power panel at @...
The Quantified Economy represents the total global addressable market (TAM) for IoT that, according to a recent IDC report, will grow to an unprecedented $1.3 trillion by 2019. With this the third wave of the Internet-global proliferation of connected devices, appliances and sensors is poised to take off in 2016. In his session at @ThingsExpo, David McLauchlan, CEO and co-founder of Buddy Platform, discussed how the ability to access and analyze the massive volume of streaming data from millio...
In the next forty months – just over three years – businesses will undergo extraordinary changes. The exponential growth of digitization and machine learning will see a step function change in how businesses create value, satisfy customers, and outperform their competition. In the next forty months companies will take the actions that will see them get to the next level of the game called Capitalism. Or they won’t – game over. The winners of today and tomorrow think differently, follow different...
“Media Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. CloudBerry Backup is a leading cross-platform cloud backup and disaster recovery solution integrated with major public cloud services, such as Amazon Web Services, Microsoft Azure and Google Cloud Platform.
According to Forrester Research, every business will become either a digital predator or digital prey by 2020. To avoid demise, organizations must rapidly create new sources of value in their end-to-end customer experiences. True digital predators also must break down information and process silos and extend digital transformation initiatives to empower employees with the digital resources needed to win, serve, and retain customers.
SYS-CON Events announced today that SoftNet Solutions will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. SoftNet Solutions specializes in Enterprise Solutions for Hadoop and Big Data. It offers customers the most open, robust, and value-conscious portfolio of solutions, services, and tools for the shortest route to success with Big Data. The unique differentiator is the ability to architect and ...
You think you know what’s in your data. But do you? Most organizations are now aware of the business intelligence represented by their data. Data science stands to take this to a level you never thought of – literally. The techniques of data science, when used with the capabilities of Big Data technologies, can make connections you had not yet imagined, helping you discover new insights and ask new questions of your data. In his session at @ThingsExpo, Sarbjit Sarkaria, data science team lead ...
A completely new computing platform is on the horizon. They’re called Microservers by some, ARM Servers by others, and sometimes even ARM-based Servers. No matter what you call them, Microservers will have a huge impact on the data center and on server computing in general. Although few people are familiar with Microservers today, their impact will be felt very soon. This is a new category of computing platform that is available today and is predicted to have triple-digit growth rates for some ...
In past @ThingsExpo presentations, Joseph di Paolantonio has explored how various Internet of Things (IoT) and data management and analytics (DMA) solution spaces will come together as sensor analytics ecosystems. This year, in his session at @ThingsExpo, Joseph di Paolantonio from DataArchon, will be adding the numerous Transportation areas, from autonomous vehicles to “Uber for containers.” While IoT data in any one area of Transportation will have a huge impact in that area, combining sensor...